Construction of the multi-family residential building "Yarielys Residence" in Gdynia

Construction as the general contractor of the multi-family residential building "Yarielys Residence" at 61-63 Abrahama St. in Gdynia, with commercial premises located on the ground floor, 6 storeys – 5 overground storeys and 1 underground storey (basement) with a built-in multi-station garage, with a terrace – recreation area, monolithic reinforced concrete structure, flat roof, including technical infrastructure, reconstruction of underground installations and demolition works.

 

Total number of apartments: 29
Number of service premises:

4

Total usable area: approx. 2.400 m2
Investor: Mostostal Gdynia Sp. z o.o., 00-217 Warszawa, ul. Konwiktorska 4

 

Linia L

The 2nd Line of the Warsaw Metro. The western part

The 2nd Line of the Warsaw Metro. The western part. Execution of complete electrical systems for the C07 station, the V08 tunnel ventilation plant, the D08 tunnel and the D09 tunnel :

  • earthing and bonding system,
  • lighting and small power systems,
  • power supply and control cables for pumping stations, basic ventilation system, local ventilation system and air conditioning system, water system valves,
  • cable supporting structures,
  • time network,
  • 15 kV MV power supply cabling,
  • stray currents measuring system,
  • traction power supply network.
Completion: December 2019
Employer:

GÜLERMAK AĞIR  SANAYİ İNŞAAT VE TAAHHÜT A.Ş., Ankara (Turcja)

Investor: Miasto Stołeczne Warszawa

 

Linia L

Dormitory at 13 Sobieskiego Street in Gdańsk

Construction of a collective seven-storey residential building (dormitory for students) with underground car park, catering and fitness services, with installations and technical infrastructure in the lot located at 13 Sobieskiego Street in Gdańsk

Altogether 476 rooms will be located in the building, i.e. in this "B-1" section will include 220 rooms (199 single rooms and 21 double rooms), while in the "B-2" section there will be 256 rooms (215 single and 41 double rooms).

.

Usable area: 18 403,78 m2
Cubature: 68 527,62 m3
Commencement: June 2018
Employer:

SILVER ROCK INVESTMENT Spółka z o.o., Gdańsk

Investor: SILVER ROCK INVESTMENT Spółka z o.o., Gdańsk

 

 

Linia L

Shell (excluding windows) of the multi-apartment building “C” as a part of the tourist and recreation complex in Chłapowo (near Władysławowo) on the plot 242/48 (Av. Żeromskiego 27)

Reinforced concrete ceilings and walls, other masonry walls made of SILKA blocks.

.

Usable area: 1 285 m2
Cubage:: 8 000 m3
Completion: July the 31st, 2018
Employer:

INWEST-HEL Sp. z o.o., Chłapowo

Investor: JK Inwest-Hel Sp. z o.o. Sp. k., Chłapowo

 

 

Linia L

The 2nd Line of the Warsaw Metro. Execution of complete electrical installations at the C17 station

The 2nd Line of the Warsaw Metro. Execution of complete electrical installations at the C17 station:

  • cables supporting structures,
  • power supply and automatic control of the ventilation room, water system valves and local pumping stations,
  • earthing, equipotential system and monitoring of stray electrical currents,
  • power supply system and lightning system,
  • power and control cabling,
  • contact line system.

 

Completion: 02.10.2018
Employer:

Astaldi S.p.A., Rome, Italy

 

 

Linia L

 

Redevelopment (expansion) of the Water Treatment Station “Brzozowa” in Gościcino (Q = 160 m3/h) with associated facilities

Redevelopment (expansion) of the Water Treatment Station “Brzozowa” in Gościcino (Q = 160 m3/h) with associated facilities, including:

  • construction of water purification plant, installation of process pipelines, installation of water pump station and inter-tank pump house,
  • demolition of a process equipment building, process water tank and raw water tank,
  • execution of new pedestrian routes, internal road system with exit from Brzozowa Street, lighting and drainage of the area, greenery,
  • execution sanitary system with terminals in the area of the Water Treatment Station "Brzozowa",
  • reconstruction of power supply and overhead line,
  • repair of treated water tanks.

 

Completion: April 2019
Employer:

Przedsiębiorstwo Wodociągów i Kanalizacji Sp. z o.o., Gdynia

 

 

Linia L

Dismantling of the traction overhead line as part of the modernization of the railway line No. 7 Warszawa Wschodnia – Dorohusk

Dismantling of the traction overhead line as part of the modernization of the railway line No. 7 Warszawa Wschodnia – Dorohusk (Stage I, section Dęblin – Lublin, km 119,500 ÷ 166,100)

.

Completion date: 08.09.2017
Employer: Astaldi S.p.A., 00156 Roma, via G.V.Bona 65 (Włochy)
Investor: PKP PLK S.A.

 

 

Linia L

 

Senior Residence

Senior Residence Residential Building with Therapeutic Centre and Nursery School in Gdańsk, Przemyska St. Construction of a complex of two buildings together with obtaining a permit to use.

The building has 89 single and double rooms with bathroom, 24 hours service facilities, nursery school, clinic and kitchen.

.

Total gross area of the building: 4 735 m2
Usable floor area of the building: 7 293 m2
Number of overground floors: 3
Number of underground storeys: 1
Completion date: the 30th of November 2018
Employer:

Millenium Inwestycje Sp. z o.o., 40-750 Katowice, ul. Hierowskiego 2

Investor: Evangelisch-Luterisches Diakoniewerk Neuendettelsau (Niemcy)
   

 

 

Linia L

Apart Hotel "Gwiazda Morza" in Władysławowo

Construction of tourist apartments building in Władysławowo, Hryniewieckiego Street. Four-storey building with underground garages, commercial units and 33 apartments.

Structure: reinforced concrete
Usable surface: 1 571,76 m2
Scope of works: cold shell, roofing works, outdoor installations
Client: Gwiazda Morza Sp. z o.o. Sp. k.a., Władysławowo

 

 

Linia L

 

 

Construction as general contractor of three residential buildings of the “Alfa Park 3 B” housing estate in Gdańsk

Construction as general contractor of three residential buildings (B1, B2, B3) of the “Alfa Park 3 B” housing estate in Gdańsk, Myśliwska / Jasieńska Street.

 A detailed description of the investment is available on the Employer's website.

 

Total number of apartments: 90
Total usable surface: 7.943 m2
Total overground cubature: 27.926 m3
Total underground cubature: 1.448 m3
Completion: 31.08.2018
Employer: Alfa Park 3 Sp. z o.o., Gdynia

 

 

Linia L

   MEGA S.A.      |      ul. Hutnicza 42, 81-061 Gdynia, Poland      |      sekretariat@megasa.pl     |      T: +48 58 667 19 00, F: +48 58 667 18 88