Project description:
Warsaw Metro – Line II. Western part. Installation of complete electrical systems for station C07, mainline ventilation chamber V08, tunnel D08 and tunnel D09; for station C08, mainline ventilation chamber V09, disassembly shaft V09A, station C09:
- installation of earthing and equipotential bonding systems,
- installation of lighting and three-phase power supply systems,
- installation of power supply and control cable networks for pumping stations, main ventilation, local ventilation and air conditioning, water supply network gate valves,,
- cable support structures,
- time system,
- 15 kV medium voltage power supply cable networks
- stray current measuring system,
- contact system,
- CCTV systems,
- installations for the fare collection system,
- installations and systems for energizing and de-energizing the third rail,
- installation of the fourth rail along section C06 - C09..
General Contractor:
GÜLERMAK AĞIR SANAYİ İNŞAAT VE TAAHHÜT A.Ş., Ankara (Turcja)
|
Project implementation time :
11.2018 – 10.2019
|
Location:
the capital city of Warsaw
|
|