In January we reported on the signing of a contract for the Wind Farm in Lodz province. And what has changed over the past six months?
The first foundation is taking shape! First, we made the primer concrete, then we battered the pile heads. Now it's time to make the steel reinforcement. Another foundation is waiting in the queue! The primer concrete has recently been poured on the next three, so any moment now they too will grow in sight. At the remaining sites, we have begun groundwork for the next foundations and are preparing to Begin the second phase of pile work.
At the same time, road and electrical work is being done.