Project description:

 

Comprehensive construction of WD-4 overpass situated at the Olszynka Interchange, constituting a part of the Southern Bypass of Gdańsk. The scope of the project included: reinforced concrete works (construction of foundations, piers, abutments, superstructure), construction of retaining walls and a drainage system, as well as all finishing works including construction of pavements, insulations and railings, and anti-corrosion treatment.

 

General Contractor:

PORR Polska Infrastructure S.A.

Project implementation start and end dates:

03.2011 - 12.2012

Span:

31,0 + 28,5 m

Length:

60 m

Carriageway width:

11 m

Location:

Gdańsk